FAR 52.242-2 - Production Progress Reports

From Knowledge base
Jump to: navigation, search
***

Prescribed in 42.1107(a)

Effective Date:1 April 1991
Clause or Provision:Clause
Provision or Clause Number: 52.242-2 - Production Progress Reports

Principle Type And/Or Purpose of Contract:
Required:
Applicable:Time and Materials/Labor Hour; Architect-Engineering; Fixed Price, Supply; Cost Reimbursement, Supply; Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Service; Fixed Price, Service; Cost Reimbursement, R&D; Fixed Price, R&D; Indefinite Delivery
Optional:Utility Services; Simplified Acquisition Procedures (Excludes Micro-Purchase); Facilities; Dismantling, Demolition or Removal of Improvements; Fixed Price, Construction; Cost Reimbursement, Construction
Subject:
ProcurementType:
Contract Threshold:
Prescription Overview:

Prescription

Clause Overview:

Clause

(a) The Contractor shall prepare and submit to the Contracting Officer the production progress reports specified in the contract Schedule.


(b) During any delay in furnishing a production progress report required under this contract, the Contracting Officer may withhold from payment an amount not exceeding $25,000 or 5 percent of the amount of this contract, whichever is less.

Important Notes/Requirements:

"Applicable to solicitations and contracts when production progress reporting is required; unless a construction contract, or a Federal Supply Schedule contract is contemplated."

Subcontract Threshold:
Incorporated by Reference:Yes
Uniform Contract Format:I
Editor:Marshall