FAR 52.232-28 - Invitation to Propose Performance-Based Payments
Prescribed in 32.1005(b)(1) | ||
Effective Date: | 1 March 2000 | |
Clause or Provision: | Provision | |
Provision or Clause Number: | 52.232-28 - Invitation to Propose Performance-Based Payments | |
Principle Type And/Or Purpose of Contract: | ||
Required: | ||
Applicable: | Facilities; Architect-Engineering; Dismantling, Demolition or Removal of Improvements; Fixed Price, Supply; Fixed Price, Construction; Fixed Price, Service; Fixed Price, R&D; Indefinite Delivery; Transportation; Utility Services | |
Optional: | Simplified Acquisition Procedures (Excludes Micro-Purchase); Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Construction; Cost Reimbursement, Supply; Cost Reimbursement, Service | |
Subject: | Invoices and Payments | |
ProcurementType: | ||
Contract Threshold: | ||
Prescription Overview: |
Prescription(b)(1) Insert the solicitation provision at 52.232-28, Invitation to Propose Performance-Based Payments, in negotiated solicitations that invite offerors to propose performance-based payments. (2) Use the provision with its Alternate I in competitive negotiated solicitations if the Government intends to adjust proposed prices for proposal evaluation purposes (see 32.1004(e)). | |
Clause Overview: |
Provision(a) The Government invites the offeror to propose terms under which the Government will make performance-based contract financing payments during contract performance. The Government will consider performance-based payment financing terms proposed by the offeror in the evaluation of the offeror’s proposal. The Contracting Officer will incorporate the financing terms of the successful offeror and the FAR clause, Performance-Based Payments, at FAR 52.232-32, in any resulting contract.
AlternateAlternate I (Mar 2000)As prescribed in FAR 32.1005(b)(2), add the following paragraph (f) to the basic provision: (f) The Government will adjust each proposed price to reflect the cost of providing the proposed performance-based payments to determine the total cost to the Government of that particular combination of price and performance-based financing. The Government will make the adjustment using the procedure described in FAR 32.205(c). | |
Important Notes/Requirements: | ||
Subcontract Threshold: | ||
Incorporated by Reference: | No | |
Uniform Contract Format: | L | |
Editor: | Marshall |
Personal notes.