Prescribed in 15.408(j)

Effective Date:1 July 2005
Clause or Provision:Clause
Provision or Clause Number: 52.215-18 - Reversion or Adjustment of Plans for Postretirement Benefits (PBR) Other Than Pensions

Principle Type And/Or Purpose of Contract:
Required:
Applicable:Time and Materials/Labor Hour; Facilities; Architect-Engineering; Dismantling, Demolition or Removal of Improvements; Fixed Price, Supply; Cost Reimbursement, Supply; Communication Services; Leasing of Motor Vehicles; Time & Material/Labor Hour; Cost Reimbursement, Construction; Fixed Price, Construction; Cost Reimbursement, Service; Fixed Price, Service; Cost Reimbursement, R&D; Fixed Price, R&D; Indefinite Delivery; Transportation; Utility Services
Optional:Simplified Acquisition Procedures (Excludes Micro-Purchase)
Subject:Post Retirement Benefits and/or Pension
ProcurementType:
Contract Threshold:
Prescription Overview:

Prescription

(j) Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions. The contracting officer shall insert the clause at 52.215-18, Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other Than Pensions, in solicitations and contracts for which it is anticipated that certified cost or pricing data will be required or for which any preaward or postaward cost determinations will be subject to Part 31.

Clause Overview:

Clause

(a) The Contractor shall promptly notify the Contracting Officer in writing when the Contractor determines that it will terminate or reduce the benefits of a PRB plan.


(b) If PRB fund assets revert or inure to the Contractor, or are constructively received by it under a plan termination or otherwise, the Contractor shall make a refund or give a credit to the Government for its equitable share as required by 31.205-6(o)(5) of the Federal Acquisition Regulation (FAR). When determining or agreeing on the method for recovery of the Government’s equitable share, the contracting parties should consider the following methods: cost reduction, amortizing the credit over a number of years (with appropriate interest), cash refund, or some other agreed upon method. Should the parties be unable to agree on the method for recovery of the Government’s equitable share, through good faith negotiations, the Contracting Officer shall designate the method of recovery.


(c) The Contractor shall insert the substance of this clause in all subcontracts that meet the applicability requirements of FAR 15.408(j).

Important Notes/Requirements:
Subcontract Threshold:
Incorporated by Reference:Yes
Uniform Contract Format:I
Editor:Marshall