Prescribed in 225.7003-5(a)(1)

Effective Date:1 March 2013
Clause or Provision:Clause
Provision or Clause Number:S 252.225-7008 Restriction on Acquisition of Specialty Metals

Principle Type And/Or Purpose of Contract:
Required:
Applicable:
Optional:
Subject:
ProcurementType:
Contract Threshold:>150,000
Prescription Overview:

Prescription

(a) Unless the acquisition is wholly exempt from the specialty metals restrictions at 225.7003-2 because the acquisition is covered by an exception in 225.7003-3(a) or (d) (but see paragraph (d) of this subsection)—


(1) Use the clause at 252.225-7008, Restriction on Acquisition of Specialty Metals, in solicitations and contracts, including solicitations and contracts using FAR part 12 procedures for the acquisition of commercial items, that—


(i) Exceed the simplified acquisition threshold; and


(ii) Require the delivery of specialty metals as end items.

225.7003-2 Restrictions

The following restrictions implement 10 U.S.C. 2533b. Except as provided in 225.7003-3—

(a) Do not acquire the following items, or any components of the following items, unless any specialty metals contained in the items or components are melted or produced in the United States (also see guidance at PGI 225.7003-2(a)):

(1) Aircraft.

(2) Missile or space systems.

(3) Ships.

(4) Tank or automotive items.

(5) Weapon systems.

(6) Ammunition.

(b) Do not acquire a specialty metal (e.g., raw stock, including bar, billet, slab, wire, plate, and sheet; castings; and forgings) as an end item, unless the specialty metal is melted or produced in the United States. This restriction applies to specialty metal acquired by a contractor for delivery to DoD as an end item, in addition to specialty metal acquired by DoD directly from the entity that melted or produced the specialty metal.

225.7003-3 Exceptions

(a) Acquisitions in the following categories are not subject to the restrictions in 225.7003-2:


(1) Acquisitions at or below the simplified acquisition threshold.


(2) Acquisitions outside the United States in support of combat operations.


(3) Acquisitions in support of contingency operations.


(4) Acquisitions for which the use of other than competitive procedures has been approved on the basis of unusual and compelling urgency in accordance with FAR 6.302-2.


(5) Acquisitions of items specifically for commissary resale.


(6) Acquisitions of items for test and evaluation under the foreign comparative testing program (10 U.S.C. 2350a(g)). However, this exception does not apply to any acquisitions under follow-on production contracts.


(b) One or more of the following exceptions may apply to an end item or component that includes any of the following, under a prime contract or subcontract at any tier. The restrictions in 225.7003-2 do not apply to the following:

(1) Electronic components, unless the Secretary of Defense, upon the recommendation of the Strategic Materials Protection Board pursuant to 10 U.S.C. 187, determines that the domestic availability of a particular electronic component is critical to national security.
(2)
(i) Commercially available off-the-shelf (COTS) items containing specialty metals, except the restrictions do apply to contracts or subcontracts for the acquisition of—
(A) Specialty metal mill products, such as bar, billet, slab, wire, plate, and sheet, that have not been incorporated into end items, subsystems, assemblies, or components. Specialty metal supply contracts issued by COTS producers are not subcontracts for the purposes of this exception;
(B) Forgings or castings of specialty metals, unless the forgings or castings are incorporated into COTS end items, subsystems, or assemblies;
(C) Commercially available high performance magnets that contain specialty metal, unless such high performance magnets are incorporated into COTS end items or subsystems (see PGI 225.7003-3(b)(6) for a table of applicability of specialty metals restrictions to magnets); and
(D) COTS fasteners, unless—
(1) The fasteners are incorporated into COTS end items, subsystems, or assemblies; or
(2) The fasteners qualify for the commercial item exception in paragraph (b)(3) of this subsection.
(ii) If this exception is used for an acquisition of COTS end items valued at $5 million or more per item, the acquiring department or agency shall submit an annual report to the Director, Defense Procurement and Acquisition Policy, in accordance with the procedures at PGI 225.7003-3(b)(2).


(3) Fasteners that are commercial items and are acquired under a contract or subcontract with a manufacturer of such fasteners, if the manufacturer has certified that it will purchase, during the relevant calendar year, an amount of domestically melted or produced specialty metal, in the required form, for use in the production of fasteners for sale to DoD and other customers, that is not less than 50 percent of the total amount of the specialty metal that the manufacturer will purchase to carry out the production of such fasteners for all customers.


(4) Items listed in 225.7003-2(a), manufactured in a qualifying country or containing specialty metals melted or produced in a qualifying country.


(5) Specialty metal in any of the items listed in 225.7003-2 if the USD(AT&L), or an official authorized in accordance with paragraph (b)(5)(i) of this subsection, determines that specialty metal melted or produced in the United States cannot be acquired as and when needed at a fair and reasonable price in a satisfactory quality, a sufficient quantity, and the required form (i.e., a domestic nonavailability determination). See guidance in PGI 225.7003-3(b)(5).


(i) The Secretary of the military department concerned is authorized, without power of redelegation, to make a domestic nonavailability determination that applies to only one contract. The supporting documentation for the determination shall include—


(A) An analysis of alternatives that would not require a domestic nonavailability determination; and
(B) Written documentation by the requiring activity, with specificity, why such alternatives are unacceptable.


(ii) A domestic nonavailability determination that applies to more than one contract (i.e., a class domestic nonavailability determination), requires the approval of the USD(AT&L).
(A) At least 30 days before making a domestic nonavailability determination that would apply to more than one contract, the USD(AT&L) will, to the maximum extent practicable, and in a manner consistent with the protection of national security and confidential business information—
(1) Publish a notice on the Federal Business Opportunities website (www.FedBizOpps.gov or any successor site) of the intent to make the domestic nonavailability determination; and
(2) Solicit information relevant to such notice from interested parties, including producers of specialty metal mill products.


(B) The USD(AT&L)—


(1) Will take into consideration all information submitted in response to the notice in making a class domestic nonavailability determination;
(2) May consider other relevant information that cannot be made part of the public record consistent with the protection of national security information and confidential business information; and
(3) Will ensure that any such domestic nonavailability determination and the rationale for the determination are made publicly available to the maximum extent consistent with the protection of national security and confidential business information.


(6) End items containing a minimal amount of otherwise noncompliant specialty metals (i.e., specialty metals not melted or produced in the United States that are not covered by another exception listed in this paragraph (b)), if the total weight of noncompliant specialty metal does not exceed 2 percent of the total weight of all specialty metal in the end item. This exception does not apply to high performance magnets containing specialty metals. See PGI 225.7003-3(b)(6) for a table of applicability of specialty metals restrictions to magnets.

(c) Compliance for commercial derivative military articles

The restrictions at 225.7003-2(a) do not apply to an item acquired under a prime contract if—

(1) The offeror has certified, and subsequently demonstrates, that the offeror and its subcontractor(s) will individually or collectively enter into a contractual agreement or agreements to purchase a sufficient quantity of domestically melted or produced specialty metal in accordance with the provision at 252.225-7010; and

(2) The USD(AT&L), or the Secretary of the military department concerned, determines that the item is a commercial derivative military article (defense agencies see procedures at PGI 225.7003-3(c)). The contracting officer shall submit the offeror’s certification and a request for a determination to the appropriate official, through agency channels, and shall notify the offeror when a decision has been made.


(d) National security waiver

The USD(AT&L) may waive the restrictions at 225.7003-2 if the USD(AT&L) determines in writing that acceptance of the item is necessary to the national security interests of the United States (see procedures at

PGI 225.7003-3(d)). This authority may not be delegated.

(1) The written determination of the USD(AT&L)—

(i) Shall specify the quantity of end items to which the national security waiver applies;

(ii) Shall specify the time period over which the national security waiver applies; and

(iii) Shall be provided to the congressional defense committees before the determination is executed, except that in the case of an urgent national security requirement, the determination may be provided to the congressional defense committees up to 7 days after it is executed.

(2) After making such a determination, the USD(AT&L) will—

(i) Ensure that the contractor or subcontractor responsible for the noncompliant specialty metal develops and implements an effective plan to ensure future compliance; and

(ii) Determine whether or not the noncompliance was knowing and willful. If the USD(AT&L) determines that the noncompliance was knowing and willful, the appropriate debarring and suspending official shall consider suspending or debarring the contractor or subcontractor until such time as the contractor or subcontractor has effectively addressed the issues that led to the noncompliance.

(3) Because national security waivers will only be granted when the acquisition in question is necessary to the national security interests of the United States, the requirement for a plan will be applied as a condition subsequent, and not a condition precedent, to the granting of a waiver.

Clause Overview:

Clause

RESTRICTION ON ACQUISITION OF SPECIALTY METALS (MAR 2013)

(a) Definitions

As used in this clause—

“Alloy” means a metal consisting of a mixture of a basic metallic element and one or more metallic, or non-metallic, alloying elements.

(i) For alloys named by a single metallic element (e.g., titanium alloy), it means that the alloy contains 50 percent or more of the named metal (by mass).
(ii) If two metals are specified in the name (e.g, nickel-iron alloy), those metals are the two predominant elements in the alloy, and together they constitute 50 percent or more of the alloy (by mass).

“Produce” means—

(i) Atomization;
(ii) Sputtering; or
(iii) Final consolidation of non-melt derived metal powders.

“Specialty metal” means—

(i) Steel—
(A) With a maximum alloy content exceeding one or more of the following limits: manganese, 1.65 percent; silicon, 0.60 percent; or copper, 0.60 percent; or
(B) Containing more than 0.25 percent of any of the following elements: aluminum, chromium, cobalt, molybdenum, nickel, niobium (columbium), titanium, tungsten, or vanadium;
(ii) Metal alloys consisting of—
(A) Nickel or iron-nickel alloys that contain a total of alloying metals other than nickel and iron in excess of 10 percent; or
(B) Cobalt alloys that contain a total of alloying metals other than cobalt and iron in excess of 10 percent;
(iii) Titanium and titanium alloys; or
(iv) Zirconium and zirconium alloys.

“Steel” means an iron alloy that includes between .02 and 2 percent carbon and may include other elements.


(b) Any specialty metal delivered under this contract shall be melted or produced in the United States or its outlying areas.

Important Notes/Requirements: