FAR 52.232-16 - Progress Payments

From Knowledge base
Revision as of 13:16, 13 September 2013 by Marshall (Talk | contribs)

Jump to: navigation, search

FAR 52.232-16 - Progress Payments

Audit Rights

  • (g) Reports, forms, and access to records. (1) The Contractor shall promptly furnish reports, certificates, financial statements, and other pertinent information (including estimates to complete) reasonably requested by the Contracting Officer for the administration of this clause. Also, the Contractor shall give the Government reasonable opportunity to examine and verify the Contractor’s books, records, and accounts.
    • (2) The Contractor shall furnish estimates to complete that have been developed or updated within six months of the date of the progress payment request. The estimates to complete shall represent the Contractor’s best estimate of total costs to complete all remaining contract work required under the contract. The estimates shall include sufficient detail to permit Government verification.