FAR 52.222-11 - Subcontracts (Labor Standards)
Prescribed in 22.407(a) | ||
Effective Date: | 1 May 2014 | |
Clause or Provision: | Clause | |
Provision or Clause Number: | 52.222-11 - Subcontracts (Labor Standards) | |
Principle Type And/Or Purpose of Contract: | ||
Required: | ||
Applicable: | Cost Reimbursement, Construction; Fixed Price, Construction | |
Optional: | Utility Services; Simplified Acquisition Procedures (Excludes Micro-Purchase); Facilities; Indefinite Delivery; Dismantling, Demolition or Removal of Improvements; Leasing of Motor Vehicles; Time & Material/Labor Hour; Fixed Price, Service; Cost Reimbursement, Supply; Cost Reimbursement, Service | |
Subject: | Subcontract(s)/Subcontractor(s) | |
ProcurementType: | ||
Contract Threshold: | ||
Prescription Overview: |
Prescription(a) Insert the following clauses in solicitations and contracts in excess of $2,000 for construction within the United States: (6) 52.222-11, Subcontracts (Labor Standards). | |
Clause Overview: |
Clause(a) Definition“Construction, alteration or repair,” as used in this clause, means all types of work done by laborers and mechanics employed by the construction Contractor or construction subcontractor on a particular building or work at the site thereof, including without limitation—
(c) The prime Contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor performing construction within the United States with all the contract clauses cited in paragraph (b). (d) (1) Within 14 days after award of the contract, the Contractor shall deliver to the Contracting Officer a completed Standard Form (SF) 1413, Statement and Acknowledgment, for each subcontract for construction within the United States, including the subcontractor’s signed and dated acknowledgment that the clauses set forth in paragraph (b) of this clause have been included in the subcontract. (2) Within 14 days after the award of any subsequently awarded subcontract the Contractor shall deliver to the Contracting Officer an updated completed SF 1413 for such additional subcontract. (e) The Contractor shall insert the substance of this clause, including this paragraph (e) in all subcontracts for construction within the United States. | |
Important Notes/Requirements: |
Construction Contract | |
Subcontract Threshold: | ||
Incorporated by Reference: | Yes | |
Uniform Contract Format: | I | |
Editor: | Marshall |