42.708 Quick-closeout procedure.
+
The contracting officer responsible for contract closeout ''''''shall''' negotiate the settlement of indirect costs for a specific contract, in advance of the determination of final indirect cost rates''', if—
(a) The contracting officer responsible for contract closeout '''shall negotiate the settlement of indirect costs for a specific contract, in advance of the determination of final indirect cost rates''', if—
+
 
* (1) '''The contract is physically complete''';
 
* (1) '''The contract is physically complete''';
 
* (2) The '''amount of unsettled indirect cost to be allocated to the contract is relatively insignificant'''. Indirect cost amounts will be considered insignificant when—
 
* (2) The '''amount of unsettled indirect cost to be allocated to the contract is relatively insignificant'''. Indirect cost amounts will be considered insignificant when—

Revision as of 15:44, 26 August 2013

The contracting officer responsible for contract closeout 'shall' negotiate the settlement of indirect costs for a specific contract, in advance of the determination of final indirect cost rates, if—

  • (1) The contract is physically complete;
  • (2) The amount of unsettled indirect cost to be allocated to the contract is relatively insignificant. Indirect cost amounts will be considered insignificant when—
    • (i) The total unsettled indirect cost to be allocated to any one contract does not exceed $1,000,000; and
    • (ii) Unless otherwise provided in agency procedures, the cumulative unsettled indirect costs to be allocated to one or more contracts in a single fiscal year does not exceed 15 percent of the estimated, total unsettled indirect costs allocable to cost-type contracts for that fiscal year. The contracting officer may waive the 15 percent restriction based upon a risk assessment that considers the contractor’s accounting,

estimating, and purchasing systems; other concerns of the cognizant contract auditors; and any other pertinent information; and (3) Agreement can be reached on a reasonable estimate of allocable dollars.

  • (b) Determinations of final indirect costs under the quickcloseout procedure provided for by the Allowable Cost and Payment (FAR 52.216-7) clause at 52.216-7 shall be final for the contract it covers and no adjustment shall be made to other contracts for over- or under-recoveries of costs allocated or allocable to the

contract covered by the agreement.

  • (c) Indirect cost rates used in the quick closeout of a contract shall not be considered a binding precedent when establishing the final indirect cost rates for other contracts.

Also see FAR 4.804 Closeout of Contract Files