Difference between revisions of "Cost or Pricing Data - Requirements Matrix"

From Knowledge base
Jump to: navigation, search
Line 5: Line 5:
 
{| class="wikitable"
 
{| class="wikitable"
 
|-
 
|-
! Area/Topic !! Agency
+
! Area/Topic !! Requirement
 
|-
 
|-
 
| Requirements: || The Contracting Officer must obtain cost or pricing data only if exceptions do not apply.
 
| Requirements: || The Contracting Officer must obtain cost or pricing data only if exceptions do not apply.
Line 13: Line 13:
 
| Limitations || Contracting Officers must not require unnecessarily the submission of cost or pricing data, because it leads to increased proposal preparation costs, extends acquisition lead times, and consumes additional contractor and government resources.
 
| Limitations || Contracting Officers must not require unnecessarily the submission of cost or pricing data, because it leads to increased proposal preparation costs, extends acquisition lead times, and consumes additional contractor and government resources.
 
|-
 
|-
| Example || Example
+
| $$ Threshholds for obtaining data:
 +
<2500
 +
$2500 to $150,000 || Example
 
|-
 
|-
 
| Example || Example
 
| Example || Example

Revision as of 11:56, 10 December 2014

Requirements for Cost Or Pricing Data

Department of Defense

Area/Topic Requirement
Requirements: The Contracting Officer must obtain cost or pricing data only if exceptions do not apply.
Exceptions: Adequate Price Competition; Prices Set by Law or Regulation; Commercial Items, Established Catalog/Market Prices; Waivers
Limitations Contracting Officers must not require unnecessarily the submission of cost or pricing data, because it leads to increased proposal preparation costs, extends acquisition lead times, and consumes additional contractor and government resources.
$$ Threshholds for obtaining data:

<2500 $2500 to $150,000 || Example

Example Example
Example Example
Example Example
Example Example
Example Example
Example Example