Difference between revisions of "FAR 52.232-15 - Progress Payments Not Included"
From Knowledge base
Line 2: | Line 2: | ||
|EffectiveDate=1984/04/01 | |EffectiveDate=1984/04/01 | ||
|ClauseorProvision=Provision | |ClauseorProvision=Provision | ||
− | |||
|Prescribedin=32.502-3(c) | |Prescribedin=32.502-3(c) | ||
− | |TypePurposeContract= | + | |TypePurposeContract=Time and Materials/Labor Hour -O; Leasing of Motor Vehicles -A; Communication Services -A; Dismantling, Demolition, or Removal of Improvements -O; Facilities -A; Indefinite Delivery -A; Transportation -A; Utility Services -O |
− | | | + | |CCSubject=Invoices and Payments |
− | |FARClauseOverview=A progress payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award. Bids conditioned upon inclusion of a progress payment clause in the resulting contract will be rejected as nonresponsive. | + | |PrescriptionOverview===Prescription== |
+ | |||
+ | '''(c)''' The contracting officer shall insert the provision at 52.232-15, Progress Payments Not Included, in invitations for bids if the solicitation will not contain one of the provisions prescribed in paragraphs (a) and (b) of this section. | ||
+ | |FARClauseOverview===Provision== | ||
+ | |||
+ | A progress payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award. Bids conditioned upon inclusion of a progress payment clause in the resulting contract will be rejected as nonresponsive. | ||
|ImportantNotesRequirements=May be included in invitations for bids if the solicitation will not contain one of the provisions 52.232-13 or 52.232-14. | |ImportantNotesRequirements=May be included in invitations for bids if the solicitation will not contain one of the provisions 52.232-13 or 52.232-14. | ||
[[Category:FAR 52 - Solicitation Provisions and Contract Clauses]] | [[Category:FAR 52 - Solicitation Provisions and Contract Clauses]] | ||
− | |||
|IncorporatedbyReference=Yes | |IncorporatedbyReference=Yes | ||
|UniformContractFormat=M | |UniformContractFormat=M | ||
|Editor=Marshall | |Editor=Marshall | ||
+ | |ProvisionClauseNumberAlternate=52.232-15 | ||
+ | |ProvisionClauseDescription=- | ||
|Checked=no | |Checked=no | ||
|HasTermDate=2014/03/31 | |HasTermDate=2014/03/31 |
Revision as of 11:40, 20 December 2014
Prescribed in 32.502-3(c) | |
Effective Date: | 1 April 1984 |
Clause or Provision: | Provision |
Provision or Clause Number: | 52.232-15 - Progress Payments Not Included |
Principle Type And/Or Purpose of Contract: | |
Required: | |
Applicable: | Leasing of Motor Vehicles; Communication Services; Facilities; Indefinite Delivery; Transportation; |
Optional: | Time and Materials/Labor Hour; Dismantling, Demolition, or Removal of Improvements; Utility Services; |
Subject: | Invoices and Payments |
ProcurementType: | |
Contract Threshold: | |
Prescription Overview: |
Prescription(c) The contracting officer shall insert the provision at 52.232-15, Progress Payments Not Included, in invitations for bids if the solicitation will not contain one of the provisions prescribed in paragraphs (a) and (b) of this section. |
Clause Overview: |
ProvisionA progress payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award. Bids conditioned upon inclusion of a progress payment clause in the resulting contract will be rejected as nonresponsive. |
Important Notes/Requirements: |
May be included in invitations for bids if the solicitation will not contain one of the provisions 52.232-13 or 52.232-14. |
Subcontract Threshold: | |
Incorporated by Reference: | Yes |
Uniform Contract Format: | M |
Editor: | Marshall |
Personal notes.