+ | "Disclosure is not confined to a formal, written submission. Instead the contractor's disclosure obligation is fulfilled if the Government obtains the data in question in some other manner or had knowledge...[It] must be meaningful, regardless of the form it takes<ref>Aerojet Ordnance Tennessee, ASBCA No. 36089, 95-2 BCA p27,922 at 139,437.</ref>. | ||
+ | |||
+ | |||
+ | |||
+ | |||
+ | ==References== | ||
+ | <References/> | ||
[[Category: Truth In Negotiations Act (TINA)]] | [[Category: Truth In Negotiations Act (TINA)]] |
Revision as of 15:17, 13 February 2020
"Disclosure is not confined to a formal, written submission. Instead the contractor's disclosure obligation is fulfilled if the Government obtains the data in question in some other manner or had knowledge...[It] must be meaningful, regardless of the form it takes[1].
References
- ↑ Aerojet Ordnance Tennessee, ASBCA No. 36089, 95-2 BCA p27,922 at 139,437.