1.  The purpose of the negotiation.
 
1.  The purpose of the negotiation.
 +
 
2.  A description of the acquisition, including appropriate identifying numbers (e.g., RFP No.).
 
2.  A description of the acquisition, including appropriate identifying numbers (e.g., RFP No.).
3.   The name, position, and organization of each person representing the contractor and the Government in the negotiation.
+
 
 +
3. The name, position, and organization of each person representing the contractor and the Government in the negotiation.
 +
 
 
4.  The current status of any contractor systems (e.g., purchasing, estimating, accounting, and compensation) to the extent they affected and were considered in the negotiation.
 
4.  The current status of any contractor systems (e.g., purchasing, estimating, accounting, and compensation) to the extent they affected and were considered in the negotiation.
 +
 
5.  If certified cost or pricing data were not required in the case of any price negotiation exceeding the certified cost or pricing data threshold, the exception used and the basis for it.
 
5.  If certified cost or pricing data were not required in the case of any price negotiation exceeding the certified cost or pricing data threshold, the exception used and the basis for it.
 +
 
6.  If certified cost or pricing data were required, the extent to which the contracting officer and contractor:
 
6.  If certified cost or pricing data were required, the extent to which the contracting officer and contractor:
 +
 
:•  (i) Relied on the certified cost or pricing data submitted and used them in negotiating the price;
 
:•  (i) Relied on the certified cost or pricing data submitted and used them in negotiating the price;
 +
 
:• (ii) Recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; and the effect of the defective data on the price negotiated; or
 
:• (ii) Recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; and the effect of the defective data on the price negotiated; or
 +
 
:•  (iii) Determined that an exception applied after the data were submitted and, therefore, considered not to be certified cost or pricing data.
 
:•  (iii) Determined that an exception applied after the data were submitted and, therefore, considered not to be certified cost or pricing data.
7. A summary of the contractor’s proposal, any field pricing assistance recommendations, including the reasons for any pertinent variances from them, the Government’s negotiation objective, and the negotiated position. Where the determination of a fair and reasonable price is based on cost analysis, the summary shall address each major cost element. When determination of a fair and reasonable price is based on price analysis, the summary shall include the source and type of data used to support the determination.
+
 
 +
7. A summary of the contractor’s proposal, any field pricing assistance recommendations, including the reasons for any pertinent variances from them, the Government’s negotiation objective, and the negotiated position. Where the determination of a fair and reasonable price is based on cost analysis, the summary shall address each major cost element. When determination of a fair and reasonable price is based on price analysis, the summary shall include the source and type of data used to support the determination.
 +
 
 
8. The most significant facts or considerations controlling the establishment of the price.  Please provide a summary for all the major cost elements.
 
8. The most significant facts or considerations controlling the establishment of the price.  Please provide a summary for all the major cost elements.
• Direct Labor
+
 
• Direct Materials
+
: Direct Labor
• Other Direct Costs
+
 
• Indirect Rates   
+
: Direct Materials
9. The basis for the profit or fee pre-negotiation objective and the profit or fee negotiated.
+
 
10. Documentation of fair and reasonable pricing.
+
: Other Direct Costs
 +
 
 +
: Indirect Rates   
 +
 
 +
9. The basis for the profit or fee pre-negotiation objective and the profit or fee negotiated.
 +
 
 +
10. Documentation of fair and reasonable pricing.
  
 
== Related Topics ==
 
== Related Topics ==

Revision as of 22:26, 17 November 2015

Contents

Negotiation Memorandum – Overview

FAR 15.406-3; Documenting the Negotiation is required of Contracting Officers in negotiations. Often times, the absence of details captured by a Contracting Officer will lead to assertions of defective pricing. As a result, best practice for contractors is to also capture the details of a negotiation. It is also best practice to distribute the negotiation memorandum to the customer/contracting officer. This does a couple things:


a. It allows for concurrence regarding the details of the negotiations, or clarification in the event of non-concurrence,
b. It also assist the customer/contracting officer in the capture of their required Negotiation Memorandum. If done in the same format, the contracting officer can simply copy many if not all of the details to their memorandum.
c. It also captures details while they are fresh in the minds of contractor personnel. Often times a post award audit may not happen until several years later, and personnel have either left the firm, or they simply cannot remember the details necessary to refute a defective pricing claim.

15.406-3 Documenting the Negotiation - Contracting Officer

The contracting officer (Primes should do the same) shall document in the contract file the principal elements of the negotiated agreement. The documentation (e.g., price negotiation memorandum (PNM)) shall include the following:

  • (1) The purpose of the negotiation.
  • (2) A description of the acquisition, including appropriate identifying numbers (e.g., RFP No.).
  • (3) The name, position, and organization of each person representing the contractor and the Government in the negotiation.
  • (4) The current status of any contractor systems (e.g., purchasing, estimating, accounting, and compensation) to the extent they affected and were considered in the negotiation.
  • (5) If certified cost or pricing data were not required in the case of any price negotiation exceeding the certified cost or pricing data threshold, the exception used and the basis for it.
  • (6) If certified cost or pricing data were required, the extent to which the contracting officer—
  • (i) Relied on the certified cost or pricing data submitted and used them in negotiating the price;
  • (ii) Recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; and the effect of the defective data on the price negotiated; or
  • (iii) Determined that an exception applied after the data were submitted and, therefore, considered not to be certified cost or pricing data.
  • (7) A summary of the contractor’s proposal, any field pricing assistance recommendations, including the reasons for any pertinent variances from them, the Government’s negotiation objective, and the negotiated position. Where the determination of a fair and reasonable price is based on cost analysis, the summary shall address each major cost element. When determination of a fair and reasonable price is based on price analysis, the summary shall include the source and type of data used to support the determination.
  • (8) The most significant facts or considerations controlling the establishment of the prenegotiation objectives and the negotiated agreement including an explanation of any significant differences between the two positions.
  • (9) To the extent such direction has a significant effect on the action, a discussion and quantification of the impact of direction given by Congress, other agencies, and higher-level officials (i.e., officials who would not normally exercise authority during the award and review process for the instant contract action).
  • (10) The basis for the profit or fee prenegotiation objective and the profit or fee negotiated.
  • (11) Documentation of fair and reasonable pricing.

(b) Whenever field pricing assistance has been obtained, the contracting officer shall forward a copy of the negotiation documentation to the office(s) providing assistance. When appropriate, information on how advisory field support can be made more effective should be provided separately.

Documenting the Negotiation - Contractor

Since the FAR required Negotiation Memorandum was designed with the intention of it being completed by the Contracting Officer, there are elements of that document that are not applicable. As such, USG contractors modify those requirements eliminating certain requirements and adding elements significant to a contractor. A Contractor’s Negotiation Memorandum would be similar to the one below.

1. The purpose of the negotiation.

2. A description of the acquisition, including appropriate identifying numbers (e.g., RFP No.).

3. The name, position, and organization of each person representing the contractor and the Government in the negotiation.

4. The current status of any contractor systems (e.g., purchasing, estimating, accounting, and compensation) to the extent they affected and were considered in the negotiation.

5. If certified cost or pricing data were not required in the case of any price negotiation exceeding the certified cost or pricing data threshold, the exception used and the basis for it.

6. If certified cost or pricing data were required, the extent to which the contracting officer and contractor:

• (i) Relied on the certified cost or pricing data submitted and used them in negotiating the price;
• (ii) Recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; and the effect of the defective data on the price negotiated; or
• (iii) Determined that an exception applied after the data were submitted and, therefore, considered not to be certified cost or pricing data.

7. A summary of the contractor’s proposal, any field pricing assistance recommendations, including the reasons for any pertinent variances from them, the Government’s negotiation objective, and the negotiated position. Where the determination of a fair and reasonable price is based on cost analysis, the summary shall address each major cost element. When determination of a fair and reasonable price is based on price analysis, the summary shall include the source and type of data used to support the determination.

8. The most significant facts or considerations controlling the establishment of the price. Please provide a summary for all the major cost elements.

• Direct Labor
• Direct Materials
• Other Direct Costs
• Indirect Rates

9. The basis for the profit or fee pre-negotiation objective and the profit or fee negotiated.

10. Documentation of fair and reasonable pricing.

Related Topics

Defective Pricing[[Category: Truth In Negotiations Act (TINA)