Difference between revisions of "Pre-Contract Costs"
From Knowledge base
(2 intermediate revisions by one user not shown) | |||
Line 1: | Line 1: | ||
+ | {{Cost Allowability | ||
+ | |Allowable or Unallowable=Allowable | ||
+ | |Regulation Source=FAR | ||
+ | }} | ||
== Pre-Contract costs <ref>FAR 31.205-32</ref> == | == Pre-Contract costs <ref>FAR 31.205-32</ref> == | ||
− | |||
'''Allowable with limitations.''' | '''Allowable with limitations.''' | ||
== FAR Summary == | == FAR Summary == | ||
+ | |||
Precontract costs means costs incurred before the effective date of the contract directly pursuant to the negotiation and in anticipation of the contract award when such incurrence is necessary to comply with the proposed contract delivery schedule. These costs are allowable to the extent that they would have been allowable if incurred after the date of the contract (see 31.109). | Precontract costs means costs incurred before the effective date of the contract directly pursuant to the negotiation and in anticipation of the contract award when such incurrence is necessary to comply with the proposed contract delivery schedule. These costs are allowable to the extent that they would have been allowable if incurred after the date of the contract (see 31.109). | ||
==References and Notes== | ==References and Notes== | ||
<References/> | <References/> | ||
− | |||
− |
Latest revision as of 09:12, 28 March 2015
Allowable or Unallowable: Allowable
Source: FAR
Pre-Contract costs [1]
Allowable with limitations.
FAR Summary
Precontract costs means costs incurred before the effective date of the contract directly pursuant to the negotiation and in anticipation of the contract award when such incurrence is necessary to comply with the proposed contract delivery schedule. These costs are allowable to the extent that they would have been allowable if incurred after the date of the contract (see 31.109).
References and Notes
- ↑ FAR 31.205-32